In order to keep being conscientious to our customers as promise, INEO’s QC strictly inspect each item before delivery. We aim to ensure all the goods are in good condition as well as qualified to meet our customer’s requirement.

INEO’s inspection process as follows:

Stainless Steel Products:

  1. Dimension: Check if the dimension is same with customer’s request.
  2. Workmanship: Make sure there is no sharp corner or edge.
  3. Thickness: Use micro-ruler to check the thickness.
  4. Material: Use exclusive chemical liquid to test the materials in order to ensure the product is using right material (SS201 or SS304)
  5. Cleaning: Make sure each item is clean before packing.
  6. Package: Check if our packing conform the Standard export package.
  7. Inspection for custom-made item: All the custom-made items will be checked more strictly.
  8. Random inspection: One or two items will be assembled to test the stability & firmness in each category.

Remark: If there is any discrepancy occurred, we will be happy to make corrections or improvements ensuring those items meet our customer’s requirement.

Refrigeration:

  1. Dimension: Check if the dimension is same with customer’s request.
  2. Workmanship: Make sure there is no sharp corner or edge.
  3. Thickness: Use micro-ruler to check the thickness.
  4. Material: Use exclusive chemical liquid to test the materials in order to ensure the product is using right material (SS201 or SS304)
  5. Cleaning: Make sure each item is clean before packing.
  6. Testing: Goods will be tested by technical machine, especially test for electricity leakage & high-pressure resistance.
  7. Inspection: Making sure there is no damage of the goods, also ensure the conformity of refrigerant, voltage and frequency.
  8. Temperature Testing: For chiller, lowest temperature, 2°C, normally can be achieved in 40mins after connected with electricity. For freezer, lowest temperature, -22°C, normally can be achieved in 1.5hours after connected with electricity.
  9. English manual: Making sure there is English manual packed along with the goods.
  10. Spare part: Making sure all the necessary spare parts will be sent along with the goods.
  11. Package: Check if our packing conform the Standard export package.

Remark: If there is any discrepancy occurred, we will be happy to make corrections or improvements ensuring those items meet our customer’s requirement.

Electric & Gas Equipment:

  1. Dimension: Check if the dimension is same with customer’s request.
  2. Workmanship: Make sure there is no sharp corner or edge.
  3. Thickness: Use micro-ruler to check the thickness.
  4. Material: Use exclusive chemical liquid to test the materials in order to ensure the product is using right material (SS201 or SS304)
  5. Cleaning: Make sure each item is clean before packing.
  6. Testing: Goods will be tested by technical machine, especially test for electricity leakage & high-pressure resistance.
  7. Inspection: Checking if the machine operates normally by connecting with electricity.
  8. English manual: Making sure there is English manual packed along with the goods.
  9. Spare part: Making sure all the necessary spare parts will be sent along with the goods.
  10. Package: Check if our packing conform the Standard export package.

Remark: If there is any discrepancy occurred, we will be happy to make corrections or improvements ensuring those items meet our customer’s requirement.